For 1/8-inch cable railing, MR-07 conceals the fitting body inside a 2-inch end post. Only the rear flange is exposed on the outside face.

Installation demonstration · 1:10English step subtitles

Before you follow the demonstration

The older hole-size segment and later grinding/release demonstrations have been omitted. Follow the current manual for aligned 12 mm through-holes and the full installation sequence. The clip includes bench handling: check the actual cable length and fitting position before any permanent crimp.

The MR-07 fitting body is fully concealed inside a 2-inch end post; only the rear flange remains outside the outer post wall. MR-07 uses 1/8-inch (3.2 mm) 1×19 stainless steel cable only. The Quick Lock end requires no crimping; the Swage end requires permanent hydraulic crimping.

Open the current installation manual (PDF)

Follow the sequence

These subtitles describe the visible actions; they are not a spoken transcript. The current model manual governs preparation, component selection and the complete installation procedure.

  1. 0:00–0:06

    Prepare the Swage-side component

    The cable and Swage-side hardware are handled on the bench.

  2. 0:06–0:13

    Crimp the Swage connection

    A hydraulic crimper is used on the Swage side. Confirm cable length, fitting position and the matching die before making this permanent connection.

  3. 0:13–0:25

    Position the fitting in the post

    The fitting assembly is positioned at the prepared metal post.

  4. 0:25–0:37

    Prepare the cable at the opposite side

    The cable is handled and cut for the run. Follow the current manual for the required installation sequence.

  5. 0:37–0:45

    Assemble the Quick Lock side

    The opposite connection is assembled. Push the matching cable fully into the Quick Lock end; that end does not require crimping.

  6. 0:45–1:01

    Apply final tension

    A hex key is used to turn the tensioner after the connections are prepared.

  7. 1:01–1:10

    Check the concealed body and exposed flange

    For the 2-inch end-post installation, check that the fitting body is fully inside the post and only the rear flange remains outside the outer wall. Confirm cable seating and alignment against the current manual.